菜单
Unjust enrichment and the six-year time limit

News / / London

Anron Bunkering DMCC v. Glencore Energy UK Ltd [2023] EWHC 295 (Comm)
This was a dispute arising under sale contracts for unleaded gasoline. The seller did not deliver all instalments due under the contracts. The buyer sought to recover the money paid in advance for the unperformed part. The Court found that the claim was time-barred, having been brought more than six years after the cause of action arose.

The background facts

On 15 July 2015, the parties entered into a contract for the sale of unleaded gasoline for delivery at Hodeida, Yemen. By a further contract dated November 2015, they entered into another contract for the sale of two further instalments. The July contract was performed but only part of the first instalment was delivered under the November contract, with the balance being delivered to a third party instead. The partial delivery took place in April 2016, but before that date, the buyer had chosen to accept the seller’s repudiation in relation to the second instalment around the end of December 2015.

The buyer had made advance payments of almost US$49 million between July and November 2015. Further payments were made in April 2016 of almost US$3.3 million. The seller sent statements of account showing overpayments of US$8.7 million on the July contract that were allocated to the November contract. With the advance payments made under the November contract, there was a total of just under US$12 million allocated to that contract. After deducting costs in respect of performance of the first instalment under the November contract, there was a balance of almost US$1,958,219.40 in the buyer’s credit. However, the seller purported to allocate this sum to various other entries in the statement of account, resulting in a minor balance owed by the buyer to the seller.

The claim

The buyer challenged this accounting and sought to recover the full balance. Its claim was brought in unjust enrichment on the ground that it was for recovery of sums that were transferred on a basis that subsequently failed.

S.54 of the Sale of Goods Act 1979 provides:

“Nothing in this Act affects the right of the buyer….to recover money paid where the consideration for the payment of it has failed”.

The buyer relied on BP Oil v. Vega Petroleum [2021] EWHC 1364 (Comm), in which the Court held that the buyer under an FOB sale contract for crude oil was entitled to its money back when it did not receive the contractual goods. Despite paying almost US$17 million under the contract, none of the oil had been delivered and there had, therefore, been a total failure of consideration. As a result, the seller had been unjustly enriched.

A claim for unjust enrichment has to be brought within six years of the cause of action arising. The seller in this case argued that the claims for money had and received were time-barred because the relevant payments were made and the alleged non-delivery occurred more than six years before the claim was issued.

The Commercial Court decision

Although the July contract had been performed and the buyer had accepted the seller’s repudiation of the second instalment under the November contract, the Court needed to consider the question whether a contract had to be terminated or discharged before an unjust enrichment claim such as this one could be brought because of the partial delivery of the first instalment. In BP v. Vega, the Court thought that termination was a necessary ingredient but found that the contract in that case had been terminated. However, in Dargamo Holdings v. Avonwick Holdings [2021] EWCA Civ 1149, the Court of Appeal identified the test as whether “the state of affairs contemplated as the basis or reason for that payment [had] failed to materialise,” although it did not need to decide the point.  

The Court in this case proceeded on the basis that, in appropriate circumstances, the test might be met without termination of the contract. In some cases, termination would be necessary e.g.  where defective goods were delivered, the buyer could not recover an advance payment, or an instalment, unless and until it had decided to reject the goods. Similarly, in the case of late delivery, if delivery remained a possibility under the contract, then it might not be possible to conclude that there was a failure of basis unless and until delivery ceased to be a possibility – which might, in reality, be only if and when the contract was terminated. However, in other circumstances, it might be concluded that the basis had failed to materialise even without any party terminating the contract.

This case was an example of the latter circumstances.Any real possibility of delivery of the first instalment of the November contract had gone by 4 May 2016, by which time the goods destined for the buyer had been delivered to Fujairah, and sold to a third party. From such time, the seller was no longer entitled to hold the advance payments, since the state of affairs contemplated as the basis for such payments, namely deliveries under the July and November contracts, had failed to materialise. Accordingly, the cause of action in unjust enrichment on the ground of failure of basis had arisen by the latest 4 May 2016. On that basis, the claim was out of time.

The Court also dismissed the argument that the statements of account constituted a statutory acknowledgment of a debt owed to the buyer because there was no admission in them of a legal liability to pay the sum which the buyer now sought to recover. Had the Court found otherwise, then time would have started to run from the date of the statements of account, 10 June 2016, potentially avoiding any time-bar.

Comment

This was a summary judgment application heard in the absence of an appearance by the buyer. The seller was, therefore, under an obligation to present the facts and arguments fairly, but had no duty of full and frank disclosure.

Consequently, the decision does not set out the circumstances surrounding the seller’s partial non-performance or explore whether the seller’s statements of account were accurate.

However, and in light of the fact that the buyer had terminated the November contract in December 2015, and the overpayment which gave rise to the balance due to the buyer had been made in April 2016, the judgment had the effect of identifying a later possible date on which to apply the statutory six-year time limit for this claim.  As a result, it may have given rise to an interesting development of the law relating to unjust enrichment in the contractual context.

A time bar argument had also been raised in BP v. Vega. In that case, however, the contract incorporated the time bar provision from BP’s general terms and conditions, which provided for a two-year time limit rather than the statutory six-year time limit that applied in this case. The Court in BP v. Vega construed the contractual time bar narrowly and found it did not apply to the buyer’s claim.

This case is a reminder that parties should keep a close eye on both contractual and statutory time-limits and be ready to take advice where there is any doubt about the applicable limit.

Joanna Steele

Joanna Steele Partner

Reema Shour

Reema Shour Professional Support Lawyer

Related sectors:

相关新闻和市场洞悉

新闻 / KSA Special Economic Zones (SEZs)

04-05-2023 / 商品与贸易, 能源及基础设施, 酒店和休闲娱乐业, 航运, 科技、媒体与电信

KSA has been actively pursuing economic diversitication for investors to do business in the Kingdom. The first Special Economic Zone has now been established, with special commercial regulations.

KSA Special Economic Zones (SEZs)

新闻 / Court construes settlement agreement in contaminated oil dispute

10-03-2023 / 商品与贸易

In this dispute arising out of the contamination of a cargo of crude oil, the Court considered whether and the extent to which the parties’ settlement agreement limited the buyer’s right to claim reimbursement for storage fees.

Court construes settlement agreement in contaminated oil dispute

新闻 / Court of Appeal considers GAFTA Default Clause and damages for non-acceptance

07-02-2023 / 商品与贸易

The Court of Appeal has considered, for the first time, the correct method of assessing damages in accordance with Default Clause 25(c) of GAFTA Contract No.24. In doing so, the Court of Appeal emphasised the compensatory principle underlying the award of damages under English law.

Court of Appeal considers GAFTA Default Clause and damages for non-acceptance

新闻 / Court confirms issuer’s liability under letter of credit

22-11-2022 / 商品与贸易

Heytex Bramsche GmbH v. Unity Trade Capital Ltd [2022] EWHC 2488 (Ch) The Court has rejected a finance company’s contention that the documents presented under a letter of credit (LC) that it had issued were discrepant, rendering the LC void. Among other things, the issuer had sought to argue that the standard UCP 600 terms that were incorporated into the LC had been modified and overriden by additional terms, such that the documents were discrepant. The Court, however, emphasised that clear notice would have to be given to effectively incorporate such additional terms which were a clear departure from the UCP 600 and which conflicted with the commercial nature of a LC. Here, any notice given was insufficient and the issuer remained liable under the terms of the LC.

Court confirms issuer’s liability under letter of credit

新闻 / Court rejects jurisdictional challenge in petroleum dispute

18-02-2022 / 商品与贸易

Addax Energy S.A. v. Petro Trade Inc. [2022] EWHC 237 (Comm) In a dispute arising out of the supply of petroleum products, the English Court has dismissed a challenge to its jurisdiction, finding that the claimant supplier had a good arguable case that an English jurisdiction clause was incorporated into an alleged oral agreement by way of course of dealing. In doing so, the Court confirmed that the evidence required to establish a course of dealing need not be extensive or consistent to meet the relevant legal test.

Court rejects jurisdictional challenge in petroleum dispute

新闻 / EU Blocking Regulation, US sanctions and contractual termination – when sanctions and business collide

18-02-2022 / 商品与贸易, 航运

In a recent ruling, the European Court of Justice (“ECJ”) was asked to consider the interpretation of Article 5 of EC Regulation No. 2771/96 of 22 November 1996 (commonly referred to as the “Blocking Regulation”) in relation to the termination, by a German telecoms company, of a contract with a bank subject to US sanctions.

EU Blocking Regulation, US sanctions and contractual termination – when sanctions and business collide